Spence Trail Building Update

We went out and rode Spence yesterday. The trails are in great shape right now and I am told the snowy section near the top is mostly gone with only a couple of hike-a-bike sections left. Trail building is proceeding well. Currently North Star has about 1.3 miles of trail cut (40% of the total?), about 1 mile of that fully groomed. The blue section of Winema is about 2/3 complete – should be completed this coming week. Queen of the Lake has about 0.9 miles left to complete, but that is some tough terrain to build in and will take a while as it is being cut entirely by hand.